Rate of Aaron: 1/15
Rate of Kit: 1/16

Let 1/t be the rate if they work together:
1/15 +1/16 = 1/t

31/240 = 1/t

t= 240/31

Therefore, together they can finish it in 240/31 days (less than 8 days)